Project LogisticsProject experience
Battery storage & early-morning dispatch

AES Alamitos BESS

Long Beach, California 2020 delivery archive · BESS

PROLINE’S ASSIGNMENT

198 inbound containers, approximately 300 outbound flatbeds, and a preloading plan built around a 7:00 AM jobsite receiving start.

inbound containers
198
53-foot flatbed loads
≈300
daily delivery start
7:00 AM
See how we operated ↓
AES Alamitos exterior view · project-reference photograph supplied by Proline
AES Alamitos exterior view · project-reference photograph supplied by Proline
HOW PROLINE OPERATED
  1. Confirm tomorrow's receiving plan

    Match the project manager's delivery sequence with truck availability, receiving capacity and crane/unloading readiness.

  2. Load the first trucks the day before

    Have the warehouse crew prepare and load the selected first-dispatch 53-foot flatbeds in advance.

  3. Hold loaded vehicles in a secured yard

    Keep the designated preloaded trucks in a secured yard overnight, ready for early release.

  4. Dispatch early for 7:00 AM receiving

    Send the first trucks out before daybreak and sequence follow-on arrivals with the site and crane crews.

Daily coordination

Proline coordinated Fluence and LG Chem teams, site/project management, trucking dispatch, drivers, warehouse loading and crane/unloading crews. Multiple daily updates and near-24/7 customer response kept the delivery plan aligned.

RESULT & OPERATING RECORD

Receiving started at 7:00 AM.

The advance-loading, overnight secured-yard staging and early-dispatch arrangement met the 7:00 AM receiving start without additional dispatch charges. Proline's historical account reports no cargo damage across the assignment.

PROJECT RECORD

Latest finalized Dispatch Logistics v3 exhibit, Proline's historical operating account and a retained November 19, 2020 project-related BOL.

198 containers and approximately 300 flatbed loads are different inbound/outbound measures. The zero-extra-charge result refers to the coordinated preloading/staging/dispatch arrangement. The retained BOL is a sample involving empty racks, not the full 300-load ledger.