Project LogisticsProject experience
Military-base delivery coordination

Davis–Monthan Air Force Base

Tucson, Arizona 2013–2014

PROLINE’S ASSIGNMENT

Transportation for a complete 16.4 MW solar installation, planned around military-base access controls.

53-foot truckloads
100+
advance submissions
≈48 hr
installation served
16.4 MW
See how we operated ↓
Davis–Monthan project photograph · SunEdison 2014 brochure
Davis–Monthan project photograph · SunEdison 2014 brochure
HOW PROLINE OPERATED
  1. Clear drivers first

    Coordinate driver screening and military-base pre-clearance before dispatch.

  2. Submit the delivery plan

    Provide delivery details approximately 48 hours ahead, including the required gate and appointment.

  3. Control the arrival

    Match each 53-foot trailer to the authorized receiving window across approximately two months of project coordination.

RESULT & OPERATING RECORD

The assignment, in context.

Transportation coordinated for the complete installation under secured-site receiving rules.

PROJECT RECORD

Finalized project exhibit 001, the SunEdison government brochure and Proline's historical transportation account.

100+ truckloads is the historical project total; it has not been presented as a completed BOL-by-BOL audit.