Davis–Monthan Air Force Base
Tucson, Arizona 2013–2014
PROLINE’S ASSIGNMENT
Transportation for a complete 16.4 MW solar installation, planned around military-base access controls.
- 53-foot truckloads
- 100+
- advance submissions
- ≈48 hr
- installation served
- 16.4 MW

HOW PROLINE OPERATED
Clear drivers first
Coordinate driver screening and military-base pre-clearance before dispatch.
Submit the delivery plan
Provide delivery details approximately 48 hours ahead, including the required gate and appointment.
Control the arrival
Match each 53-foot trailer to the authorized receiving window across approximately two months of project coordination.
The assignment, in context.
Transportation coordinated for the complete installation under secured-site receiving rules.
PROJECT RECORD
Finalized project exhibit 001, the SunEdison government brochure and Proline's historical transportation account.
100+ truckloads is the historical project total; it has not been presented as a completed BOL-by-BOL audit.