Project LogisticsProject experience
Import staging & construction release

Regulus Solar Project

Lynwood & Kern County, California Historical SunEdison program

PROLINE’S ASSIGNMENT

Port arrivals buffered in a dedicated warehouse, then released when the construction site was ready.

import containers
≈700
sq ft warehouse
≈200,000
53-foot deliveries
400+
See how we operated ↓
Proline warehouse archive · solar-module staging context
Proline warehouse archive · solar-module staging context
HOW PROLINE OPERATED
  1. Recover and stage imports

    Coordinate drayage from the port into a dedicated approximately 200,000 sq ft warehouse in Lynwood.

  2. Hold the inventory

    Stage the solar cargo for approximately four months before full outbound execution.

  3. Release with the project manager

    Coordinate more than 400 trailer deliveries over approximately three months, averaging about 10 per delivery day.

RESULT & OPERATING RECORD

The assignment, in context.

The project account reports no cargo damage and on-time delivery, with outbound volume and timing coordinated to the jobsite plan.

PROJECT RECORD

Finalized Regulus project exhibits and Proline's historical operating account.

Container count, warehouse area, durations and daily pace are historical approximations; they are not added together as one shipment total.