Spectrum Solar Project
North Las Vegas, Nevada 2013
Warehouse storage followed by construction-sequenced dispatch, with one truck scheduled each hour.
- 53-foot deliveries
- 159
- loads per delivery day
- ≈8–10
- on-time arrivals
- 100%

Store before construction
Receive and hold the solar-module crates in warehouse storage until the installation schedule called for them.
Release to the field plan
Dispatch approximately 8–10 trailers per delivery day against the jobsite manager's approved release sequence.
Keep the hourly rhythm
Schedule one truck each hour so arrivals followed the field team's receiving plan.
The assignment, in context.
No late arrivals reported across 159 trailer deliveries. The site team gave Proline a full-score performance evaluation.
Finalized project exhibit 002, warehouse archive imagery and Proline's historical delivery and evaluation account.
The 8–10 loads/day figure is approximate; the 159-delivery total and on-time outcome describe this project assignment.